1. The overview of SharePoint TaskMaster after add some task and make them relation ship.
2. After setup look like then click on New Item
3. New Item
4. Context menu with Edit Item
5. Click Add Row to column settings
6. Click Recalculate to calculate duration and work for each task
7. Duration was recalculated
8. Assign resource for each task
9. Assign parent task
10. Assign predecessor task
11. Working hours and language setting
12. After add more tasks and change value of some parent and predecessor tasks
13. Include milestone
14. Choose and click edit multi items
15. Edit multi items form look like